Celtic Anglian
Water
Celtic Anglian
Water (CAW) was established in 1998 to participate in the development
of Ireland's water and wastewater infrastructure. CAW is a 50/50
joint venture company between National Toll Roads and Anglian Water
International plc (part of the Anglian Water Group).
CAW operates in the development of water and wastewater
assets - providing water supply, wastewater treatment, plant operation
and maintenance services for both industrial and municipal clients.
The joint venture combines the in-house technical expertise of AWG
plc with NTR local knowledge of the Irish market.
Services
Celtic Anglian Water offers a unique service to both industry and
local authorities, by way of water and wastewater plant operational
services. The company can provide a secure and cost-effective solution
to water and wastewater problems. Recently, the company has diversified
into the Water Metering Industry with great success and is currently
running the Galway County Non-Domestic Metering System.
The efficient operation and management of treatment
plants ensures that correct constant standards can be achieved and,
ideally, a reduction in cost can be delivered by optimising chemical
and electrical usage. Frequently, through better management procedures,
less sludge is produced by the plant and, with today's escalating
costs, these savings can be significant.
Water Projects
Galway County Non-Domestic
Metering, DBO Contract
Description
This Contract includes for the design installation and operation
and maintenance of 12,370 non-domestic meters in Galway County.
The contract also has an option for the provision of a customer
call centre, billing system and debt collection service.
Process
In this project, Celtic Anglian Water Ltd (CAW) is the lead contractor,
with Coffey Construction as the appointed sub-contractor to provide
the pre-instasllation survey and meter installations.
|
CAW is responsible for -
- Customer Database Validation
- Establish Meter Reading System
- Establish Billing System
- Establish Debt Recovery Procedures
- Establish Customer Call Centre
- Operations of Meter Reading and Maintenance, Billing Debt
Recovery and Customer Care.
|
Value
€10.8 million.
Contract Period
2006-2018.
Client
Galway County Council
Sligo and Environs Water Supply Scheme
This is an operation & maintenance contract for Sligo County
Council, which includes -
- the water treatment works in Foxes Den
- the intake Pumphouse in Cairns (Lough Gill) - and
- two kilometres of raw water rising main between the intake
pumphouse and the water treatment works, with an output of 11,000
m3 per day.
|
The treatment process comprises of: |
|
inlet screenings; |
|
raw water pumping; |
|
flocculation; |
|
flotation using dissolved air; |
|
rapid gravity filtration; |
|
chlorination; |
|
fluoridation. |
The value of the contract is €6.3 million and covers the period
2001-2011.
Dublin Region Water Conservation Project (DRWCP)
The DRWCP was awarded to Anglian Water Ireland. The project
covered seven separate Local Authorities, servicing a population
of 1.3 million people.
It was initiated to reduce unaccounted for water (UFW) in the Dublin
region distribution network. The existing UFW was understood to
be in excess of 40% and the driving objective of the project was
to reduce this by 50%. The contract was jointly funded by the EU
and the DOELG and split into 3 phases -
- study
- construction -and
- maintenance.
Skills transfer from Anglian Water Ireland to Local Authority staff
was a key component in the success of the project. The water conservation
project involved:
- infrastructure design and installation;
- data analysis;
- leak location and repair;
- mains rehabilitation;
- pressure management;
- analysis of commercial use;
- meter accuracy;
- pressure change.
The total value of the contract was €35 million and covered
the period 1997-2002.
Wastewater Projects
Ringsend Wastewater Treatment Works
Since 1906, Dublin's wastewater received only primary treatment
with the removal of screenings, grit and settleable sludge, which
was dumped offshore in the Irish sea by a dedicated sludge ship.
Wastewater from the north of the city was discharged untreated into
the sea off Howth.
The introduction of the Urban Wastewater Treatment Directive
(1991) - together with the water quality standards laid down
in the EU directive on Bathing Water (76/160/EEC), demanded
an improved level of wastewater treatment and water quality
in the bay.
It was this legislation that led to the planning of the Dublin
Bay Project in 1994.
|
|
This design, build and operate (DBO) contract for Dublin City Council,
upgraded the existing wastewater treatment facility at Ringsend
to meet EU and Dublin Bay Water Quality Standards - by providing
secondary and tertiary treatment for a population equivalent of
1,700,000.
The contract was awarded to the ABA consortium, comprising of -
Ascon, Black & Veatch and Anglian Water International on a Design,
Build and Operate basis.
Ascon, an Irish construction firm, has specific responsibility
for the design and construction of all civil, building and architectural
works for the project.
Black and Veatch through its UK subsidiary, Black and Veatch Contracting
Limited is responsible for the design, supply, installation and
commissioning of the mechanical, electrical and process equipment
of the works.
Celtic Anglian Water is responsible for the operation and maintenance
of the new and existing works for 20 years.
|
For the first time ever, the beach at Dollymount Strand on
Dublin's northside has been awarded a coveted Blue Flag by
the International Blue Flag Jury.
According to the International Jury, the quality of bathing
water and surrounding beaches in Dublin Bay has improved dramatically
over recent years and the Ringsend Wastewater Treatment Works
(WwTW) has been credited as having made a significant contribution
to the improvement in water quality standards.
|
The contract value is €250 million and covers the period 2002-2022.
Sligo WwTW
Description
This design, build and operate contract for Sligo County Council
will build a wastewater treatment facility at Fanisklin to meet
EU and Irish Goverment Standards, by providing secondary and tertiary
treatment for a population equivalent of 80,000.
Project Partners
Anglian Water Group is the main Contractor, with Celtic Anglian
Water as a Sub-contractor handling Operation & Maintenance Phase,
with Coffey Construction & Enpure as sub-contractors for the Design
Build Phase.
Process
The plant will provide lamella plate settlement, along with SBR
technology to achieve BOD/COD removal and partial nitrification.
Process treatment will include -
- screening;
- grit removal;
- odour control;
- clarification;
- biological treatment using Sequential Batch Reactor Technology;
- UV disinfection.
Sludges are treated by digestion and thermal drying - and re-used
as a fertiliser conditioning material in agriculture.
Value
€36 million.
Contract Period
2006 -2028.
Client
Sligo County Council.
Consulting Engineer
Jennings O' Donavan
Waterford WwTW
Description
This design, build and operate contract for Waterford City Council
will provide a wastewater treatment facility at Gorteens to meet
EU and Irish Goverment Standards, by providing secondary and tertiary
treatment for a population equivalent of 189,000.
Project Partners
Anglian Water Group is the main Contractor, with Celtic Anglian
Water as a Sub-contractor handling Operation & Maintenance Phase
with Coffey Construction & Enpure as sub-contractors for the Design
Build Phase.
Process
The plant will provide lamella plate settlement along with SBR technology
to achieve BOD/COD removal and partial nitrification. Process treatment
will include -
- screening;
- grit removal;
- odour control;
- clarification;
- biological treatment using Sequential Batch Reactor Technology;
- UV disinfection.
Sludges are treated by digestion and thermal drying - and re-used
as a fertiliser conditioning material in agriculture.
Value
€53 million.
Contract Period
2006 -2029.
Client
Waterford City Council.
Consulting Engineer
Mott Mc Donald Pettit.
Celtic Anglian Water aims to become the leading water and waste
water service provider in Ireland. In order to realise its objective,
the company continues to maintain an excellent product quality -
together with achieving clients' expectations of service, expanding
the business and operating in a safe and sustainable way.
Because Celtic Anglian Water is a major provider of water and environmental
services in Ireland, the environment is central to its business.
CAW takes water from the environment, treats it and puts it into
supply. The company receives and treats wastewater before returning
it to the environment.
It is a stated objective of the company to strive for improvements
in its environmental performance, the conservation of resources
and the adoption of best environment practice. CAW is committed
to the sustainable management of the environment, while at the same
time, providing value for money to its clients.
In particular the company has stated that it will:
- Aim to prevent pollution and meet fully its legal obligations
to the environment.
- Continue to develop and improve its wider environmental performance.
- Continually assess the environmental impact of all its activities.
- Measure its performance against specified targets.
- Promote a wider understanding of environmental issues amongst
its employees, customers and suppliers - and
- Achieve ISO 14001 accreditation for those contracts that require
it.
For further information on Celtic Anglian Water, Click
Here
|